CEILING REFURBISHMENT AT UPSI TANJUNG MALIM

PROJECT: CEILING REFURBISHMENT AT UPSI TANJUNG MALIM

A birdcage scaffold served as the working platform, utilizing a medium-duty tubular design. The standard distance between uprights was 1.8 meters, with a lift distance of 2.1 meters. The design and drawings were provided by Silara Akses and endorsed and calculated by a Professional Engineer (PE). A team of 9 scaffolders completed the erection in four days and the dismantling in two days, with both tasks handled by Basic and Intermediate scaffolders, monitored by a highly experienced supervisor. After installation, the scaffold was inspected by an advanced inspector. The project was successfully completed without any technical issues, with all materials supplied by Silara Akses.

Require a reliable scaffolding contractor? Reach out to us to learn more!

Write a comment

8 − 1 =